默认 precast parking garage questions

precast parking garage questions
working on my first parking garage. it is a hybrid structure of precast columns, beams, double t slabs and cast in place shear walls. lateral loads to be transfered to shear walls by floors acting as rigid diaphragms. 3" cast-in-place topping will be provided.
questions:
1-what are considered to be the diaphragm chords? the l-beams or some type of additional reinforcing?
2- who designs these chords; the precast engineer or the engineer of record of the building?
3- who designs the connections between different precast elements to resist lateral loads?
thanks for the help
find a job or post a job opening
in my (brief) garage experience:
1) i've provided reinforcement in the topping slab to act as diaphragm chords.
2) the eor is typically responsible for lateral analysis. precasters will provide the design of the gravity system and all connections. the eor is usually responsible for the foundation system and any cip concrete pilasters, slab-on-grade, or retaining walls that may be required.
3) the precaster will provide connections between precast elements and shear walls based on the lateral forces you indicate. i've typically provided a shear wall schedule with forces in the walls at each floor.
one bit of advice -- talk to a local precaster. or, if the contractor is on board early, talk to their proposed precasters. they are usually very helpful, and will assist you with many of your questions.
details are important, esp. if this is your first project. before the precaster is brought on board, you will need to make sure that the tt layouts are reasonable based on spans and bay dimensions (use the pci manual). you'll also need to make sure the depth of your it beam will allow enough clearance based on the floor/floor heights. detail tooled joints between the tt's, give special attention to the drainage layout, make sure your shear walls can be attached to the diaphragm (i.e. they're on the correct side of stairwell/elevator openings, as precast drag connections are seldom practical).
that's a start -- again, talking to a precaster early is worth it's weight in gold... they'll usually look at a preliminary plan and details and offer great advice early in the process.
jkstruct,
thanks for you input. what are the alternatives typically done to providing reinforcement in the topping slab to act as diaphragm chords?
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
parking garage live load huangyhg 产品功能分析 0 2009-09-15 11:27 AM
nbc 2005 parking garage live load huangyhg 产品功能分析 0 2009-09-10 03:43 PM
concrete garage deck collapses huangyhg 产品功能分析 0 2009-09-08 12:12 PM
analyzing parking garage for large crowd of people huangyhg 产品功能分析 0 2009-09-07 11:42 AM
30mpa parking garage concrete slab vs. 35mpa huangyhg 产品功能分析 0 2009-09-07 08:39 AM


所有的时间均为北京时间。 现在的时间是 05:05 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多