here is my condition:
2 way plate pt parking structure. i have "i" shaped shear walls in the middle of the building with only 45' of slab beyond the walls on either end. my columns align with the wall where i would want to string my banded tendons thru the wall. do i terminate the tendons at the face of the wall or do i string them thru the wall at the center of gravity of the slab. by the way - stringing thru doesn't necessarily mean running down the center of the wall it will mean puting cables on either side and some down the middle.
bump!
still no input?
i am not going to be much help because i have only came across this situation one time and my practical pt experience is limited, but i will try. i had a similar situation with a one way pt garage where there was a large beam framing into the end of the wall (beam longitudinal axis was parallel to the longitudinal axis of the wall) and i decided not to stop the tendons at the end of the wall because i was afraid of the shrinkage and creep that could bust the slab around the interface to the wall. in fact, i ended up using a reinforced concrete beam instead of a pt beam at this location with connections specified to be installed later in the project phase.
your idea of running the tendons along either face of the wall at the center of gravity sounds better than stopping all that force at the end of a large shearwall. i would think the movement of the slab in time could cause an issue at this location if you were to try and restrain the force resulting from stopping the tendons. maybe jae can help more when he comes back from his hiatus.
the deplorable mania of doubt exhausts me. i doubt about everything, even my doubts.
-gustave flaubert
not sure of the value of my input here - but i would think you'd want to lap the tendons past the wall some distance to ensure a "soft" tie-in between the slab and walls.
terminating your tendons, and the resulting prestress, at the same place there is an abrupt geometric change doesn't sound very good to me.
dougantholz,
probably because more info is required to answer it properly.
presumably the tendons need to resist a maximum negative moment at the wall so they will be at a high point there. they need to extend well past this point to transfer the force to the wall reinforcement. if the slab is extending along with the wall then i would make make the tendons continuous. they could drop down to the centre of the slab a few metres past the start of the wall.
i have seen people detail beams joining to a longitudinal wall cog the bars down at the back face of the beam. this is useless. the tension force in the bars needs to be transmitted to the wall concrete and reinforcement. otherwise no negative moment capacity will be generated. there will simply be a big crack immediately after end of the bars. its is not just a shrinkage/creep problem, the force in the reinforcement from flexure needs to go somewhere.
your concept or continuing the banded strands along the axis of the wall is correct. think of it as a long column and keept the strand pattern as if it were passing through a column.
i recommend keeping the strand pattern at the same height until you are clear the support. when checking the strand before placing concrete, it is important that the strand not have a dip in the flat profile. otherwise the upward force could pop off a piece of slab. this sometimes happens on slab bottoms when there is a hump in the flat area of the strand. when the force is applied it will blow out the bottom of the slab. it's scary, but you can grout around the strand, patch the slab, and keep going.
if at all possible, the shear wall should be near the center of the stessing pattern to avoid cracking in the slab. this can be accomplished with a 36" wide pour strip to separate the different slab pours.
thanks florida! that was exactly what i was looking for.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
masonry wall on slab on grad huangyhg 产品功能分析 0 2009-09-10 12:57 PM
in enercalc masonry wall design, what is parapet heigh huangyhg 产品功能分析 0 2009-09-09 07:17 PM
hairline cracks in post tensioned slab huangyhg 产品功能分析 0 2009-09-09 03:43 PM
foundation wall tied to s.o.g huangyhg 产品功能分析 0 2009-09-09 01:39 PM
foundation wall 40 feet below grade huangyhg 产品功能分析 0 2009-09-09 01:38 PM


所有的时间均为北京时间。 现在的时间是 07:09 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多