默认 h-pile to pile cap attachmen

h-pile to pile cap attachment
i am looking for clever ways to attach a steel h-pile to the concrete pile cap...considering uplift.
i know of the steel plate welded to the top, but i have overthought that and am not comfortable with a potential cavity under the plate.
i have used a "v" shaped rebar threaded through a hole in the top of the pile and extending vertically into the cap, but there was some difficulty during construction. the bar was tough to deal with around the bottom mat of bars and sequencing with the formwork and bottom mat placement was also painful.
does anyone have any ways to have a positive connection between the steel pile and the pile cap?
thanks in advance.
check out our whitepaper library.
how about headed shear studs or welded angles or rebars?
concur with peinc. have also used welded shear studs attached to top of h-pile for uplift conditions in the past.
we have used a hooked rebar welded to the web of the h-pile.
this seemed to work well, and was easy for the guys to work around on site.
i think you'll get prying action if you use angles.
i don't like welding rebar. i actually have never allowed it because it is so brittle.
here you go:
1) conceptially flip your pile so it looks like a column.
2) calculate what size headed anchor bolts you would need to develop the tension. try to stay with a307/a36
3) determine the depth of concrete you need to develop. (you might need to go with plate washers on the bolts to develop the tension.)
4) weld a36 threaded bars meeting your design to the four corners of the outside flanges using a flare bevel weld. you'll need to calculate your length of weld.
5) tack weld the nuts on. (double nut it if the plate washers if needed)
that should take care of it. i'm sure there are other ways, but this is my preference. if you only need two bolts, locate them at the centerline of each flange (along the web).
chip
thanks for all of your input!
i like the ideas of having a connection that looks like a concrete pile connection (vertical dowels). i tried to stay away from welding the "dowels" but your responses show its really not that big of a deal.
thanks.
chipb,
welding of reinforcement is okay as long as you specify it done to the approriate procedure
ansi/aws d1.4/d1.4m:2005 covers this.
as long as it is done correctly then it is no more brittle than any other welded connection.
regards
csd
instead of a "v" shaped bar thru a hole in the web, i have used a straight bar. not as good a "v" bar, but good enough for a lot of applications - for moderate uplift the rebar cage in the cap is going to keep this horizontal bar from pulling out the bottom.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
h piles - end bearing huangyhg 产品功能分析 0 2009-09-09 03:39 PM
h pile huangyhg 产品功能分析 0 2009-09-09 03:39 PM
h pile to pile cap connection huangyhg 产品功能分析 0 2009-09-09 03:38 PM
embedmentextension of piles into the pile cap huangyhg 产品功能分析 0 2009-09-08 10:14 PM
adjacent pile cap huangyhg 产品功能分析 0 2009-09-07 10:18 AM


所有的时间均为北京时间。 现在的时间是 07:08 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多