默认 glulam arch question

glulam arch question
designing a swimming pool enclosure that has three-hinged glulam arches. in the parallel direction the arches handle the wind load. since the roof structure will be purlins framing to the arches and not bearing on the perimeter wall i say there needs to be a wind girt at the top of the wall that will span between the arches, similar to pre-engrd mtl bldgs. a colleague has convinced the contractor that the walls's double top pl does the job and no wind girt is needed. what do you guys say?
lmao!! thanks! i needed a good joke!
you're using a glulam top plate too, right.
(did i answer your question?)
are you talking about wind in the direction parallel to the arches?
with a stud wall you need to get the wind load into the roof diaphragm. the diaphragm then will transfer the wind load into the arches. the double top plate may be required to serve as a diaphragm chord.
depending on the length of the top plate and the sizes, it is possible. how do you plan on getting the wind loads into the foundation. just getting it into the diaphragm with your double top plate (or whatever method you come up with is one thing). once in the diaphragm, you have to get it into the foundation.
do you have shearwalls or any kind of moment connections between the purlins and the arches for the perpindicular direction?
rarswc-
he said that the wind parallel to the arches would just be handled by the arches, which makes sense. his question is for wind perpindicular to teh arches.
whoops. sorry. duh. must have had a bad brain day yesterday (as compared to other days.)
i second structuraleit and his questions.
i'm actually kind of shocked someone is doing this over a pool. i'd think the humidity combined with the chlorine would not be very good for either the wood or the glue. i've seen concrete t beams significantly deteriorate under the same use.
the way i read the original post, he is talking about wind parallel to the arches, and he has a wall perpendicular to the arches which needs its top reaction transferred to the arches. he did say that the member in question would span between the arches.
if that is the question, engrman, you do need either diaphragm action or a horizontally spanning
chipb,
there are lots of pool roofs done in glulam all over the world. needs attention to detail, specification of appropriate grade, coatings, condensation control, etc. glulam is material of choice in many areas.
hokie66, you are right i was talking about wind parallel to the trusses. there is a diaphragm. it just seemed to me that with an 8/12 pitch the connection at the wall gets a little flaky and a wind girt would do a better job of transferring the wall lateral load. maybe the blkg btwn the wall and first purlin does the job.
chipb, timberweld, the glulam fabricator, is aware of the enviromental concerns and the specifications cover it.
everybody else, thanks for the replies.
well, you learn something new everyday. the church i grew up in had glulam arches. since then i've always been partial to glulam arches.
this is going to depend on your connection detail at this eave. either way, you're going to have to transfer tension and shear at this location. you can do it with a double top plate, just make sure you get all the forces transfered. personally, i'd probably tension strap the plates across the outside face of the arches, and transfer the shear directly to the arches.
in the direction we are talking about, i don't see where diaphragm axial chord forces come from, as each arch takes its part of the load. unless there is a need for load sharing.
hokie66
you are still getting axial chord forces between the arches, and the shear is transferred to the arch.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
brick arch huangyhg 产品功能分析 0 2009-09-07 04:47 PM
atrium column unbraced length question huangyhg 产品功能分析 0 2009-09-07 01:49 PM
profile and datum question huangyhg tec-ease(America) 0 2009-09-05 12:20 PM
【转帖】what is arch e size yang686526 American standards 0 2009-05-04 11:15 AM


所有的时间均为北京时间。 现在的时间是 11:51 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多