wire initial tension in guyed stack
can someone advise the typical initial tension of the wires? some structural design guide suggests a 1/8 breaking strength of the wire (iwrc).
the stack (foundation) i’m designing is about 300ft tall, two sets of guys. the vendor’s information is not quite available yet.
thanks in advance.
find a job or post a job opening
depends on the angle with the vertical. the compressive, (vertical), component is the limiting factor. the total downward force from all oriented guys will have to be less than the safe compressive strength of the mast/chimney/stack. i use an upper limit of 50% of yield for horizontal guys and proportionally less for lesser angles from vertical.
try looking through this thread
the cicind code for steel chimneys recommends that the pretension should be between 15 and 30 percent of the maximum tension due to design wind under the hot condition.
you also need to look at deflection of the cables as well as the stack.
the higher the initial tension the less the cables will sag.
also the higher the tension the less the lateral deflection of the stack.
so there is a trade off between strength and deflection in this case.
j1d,
these are things i have had to deal with, with respect to bottom pinned guyed stacks approximately 300 ft.
vibrations
guy galloping
fatigue cracking in the lower region of the stack
i have found the typical guy tensions are not really applicable in my experience and may require monitoring by the owner.
hth
vod
thanks very much for the information.
i'm waiting for the vendor's data for the initial tension, which determines directly the deadmans.
on the other hand, the amount of initial tension doesn't seem to affect the shaft deflection too much, while the upper guy's elevation does. from the preliminary diagram, the free-standing section of the stack above the upper guys is about 85ft, this not only causes big bending at the guyed location, also introduces a huge vortex shedding of wind gust on the cantilever portion.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
pretension load for guy wire supported flare stack huangyhg 产品功能分析 0 2009-09-15 02:45 PM
multi span cable huangyhg 产品功能分析 0 2009-09-10 03:25 PM
guyed stack design huangyhg 产品功能分析 0 2009-09-09 03:33 PM
guy initial tension huangyhg 产品功能分析 0 2009-09-09 03:32 PM
calculation of guy wire length for tall guyed mas huangyhg 产品功能分析 0 2009-09-07 10:07 PM