默认 wall panel dead load

wall panel dead load
is the vertical dead load of metal wall panel supported by the girts or the foundation/slab/grade beam? we have 100 feet tall building and someone is telling me that the full weight of the wall panel is supported by the grade beam around the perimeter. which means the wall panel has to support it's own cumulative weight. at the same time, i haven't seen girts designed for anything but wind load.
we don't ever put vertical dead load into girts (except self weight - and thus sag rods) so we assume it all goes to the grade beam.
i think the girts transfer vertical dead load into the connections to cols and then that load plus any cumulative load is transfered to the column foundation. i do not assume the grade beam takes all the cumulative load from the panels above.
regards,
rarebug
so, twinnell....either way!
what is a grade beam?
in this case it would be a concrete beam at grade carrying vertical load (how much is left to the reader here) to the concrete footings beyond.
you could also design it as a strip footing, but maybe the dead load is needed at the footings for overturning...????
mike mccann
mccann engineering
twinnell:
when you say "girts", i visualize horizontal steel members spanning between steel mainframes of a metal building.
horizontal girts.
cool situation. if the wall weighs 4 psf (2 psf panel + 2 psf other stuff), then that's 400 plf at the bottom. it would be interesting to check the wall panel itself for combined bending and column buckling for the length from the foundation to the first girt. i have no clue how that would work out because some of those are pretty darn skinny and the first girt might be 8-10' (guess) from the foundation. might need to put the first few girts closer together to cut down the column buckling unbraced length.
thanks mssquare48
last job i completed was girts spanning approx 9m and with 2 rows of sag struts. at the bottom of the bottom girt 2 short struts were put in propped from the panel and straightening the girt system as they are very weak in the vertical direction even under their own dead load.
my normal practice is to support the cladding vertical load at the top, not the bottom. the girts are designed for horizontal load only. the cladding distributes the vertical loads by diaphragm action to the sag rods or other vertical supports which are in tension. but there are other ways of doing it, and it depends somewhat on the type of cladding. i would avoid relying on the cladding for much capacity in compression.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
partition live load huangyhg 产品功能分析 0 2009-09-15 11:35 AM
in enercalc masonry wall design, what is parapet heigh huangyhg 产品功能分析 0 2009-09-09 07:17 PM
foundation wall 40 feet below grade huangyhg 产品功能分析 0 2009-09-09 01:38 PM
effects of a load on sog and below grade huangyhg 产品功能分析 0 2009-09-08 09:45 PM
concrete basement wall design huangyhg 产品功能分析 0 2009-09-08 11:39 AM


所有的时间均为北京时间。 现在的时间是 02:53 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多