默认 ubc section 3402.2 9existing structures0

ubc section 3402.2 (existing structures)
i have situation where i am adding 4' of new parapet to an existing building (only about a length of 20'). this will cause some drifting. i seem to be confused everytime i do something with an existing structure. at this time it is not known the size of the roof bar joists. i do have spans and spacing and so forth. the way i see section 3402.2 is that i shall calculate the load on the joists according to loads specified by the building code when the building was built. then add the snow drift according to the governing code today. if the increase force due to the drift is less than 5% then i'm good to go.
thanks for the help
check out our whitepaper library.
that's what i would do. worst case scenario is having to weld in new web reinforcement (angles or a706 rebar) on the existing bar joist for the extra end shear due to drifting. flexure might be a problem in the top chord.
look very carefully at all the bar joists at the ends. often times, the old bar joists have an metal "dog tag" that calls out the type and series of the joist.
sji publishes a historical book of all the old load tables for old joist callouts. if you can find out what size joist you are dealing with, you may be able to infer the shear capacity of the joist directly in lieu of capping it at 105% of what it was carrying.
if you can't find a dog tag, then you might could tell what kind of bar joist you are dealing with using caliper and a machinist's ruler.
thanks sundale
thats the process i normally go through. so i'm familar with the tags and sji and so forth. this building had a remodel about 4 years ago a another parapet was added to the building adjacent to where i'm adding a parapet. all the joists and spans are the same. and no additional reinforcing of those josts had to be done. i just wanted something quick and easy that i could fall back onto instead of running out to the site and taking measurements and so forth. not that i'm taking the easy way out. i'm want to take the logical way out.
thanks
no worries wale01.
the last time i had to do this sort of thing, we added a quite tall parapet to an existing building so that it retained all the drifted snow from our modified roof and did not load the neighbor's existing roof with a new snow drift load. not an elegant solution, but the building department agreed with the concept.
reinforcing the bar joists was not easy to design and was even worse to construct in the field given an existing building (hat factory) with plumbing, mechanical, etc. all in the way of the welders. the fire danger was an issue too if i recall.
wale01, can you limit the length of the parapet to 15 feet instead of 20 feet? then you would not be required to design for drifting snow at all.
sundale, adding a parapet does not necessarily eliminate snow drifting considerations for the adjacent building. the parapet can act as a projection that traps snow if the adjacent building is upwind and deposit it on the adjacent building. was this considered in your case?
the adjacent building was many feet lower with a horizontal separation of something like 5'-0". this was 10 years or so ago...
the idea was to create a tall projection on our higher roof to prevent snow from our windward roof depositing onto the neighbor's lower and leeward roof.
our projection would not have created a windward drift from the their roof.
we have done hundreds of buildings where we reinforce the existing structure. the easiest way that we have found is welding new rods into place in the top and bottom chords, and web members as required. we have also substituted a plate on the bottom chord (half the welding). don't forget to also check the joist shoes, easiest way we have found to fix them is to jam them tight with grout.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
confused with aisc code about section modulus huangyhg 产品功能分析 0 2009-09-08 01:07 PM
built up section - sction modulus huangyhg 产品功能分析 0 2009-09-07 05:46 PM
section of a section huangyhg tec-ease(America) 0 2009-09-05 12:48 PM
【转帖】section of a section yang686526 American standards 0 2009-04-29 09:53 PM
【转帖】asme美国机械工程师标准目录2 huangyhg American standards 5 2009-04-26 02:38 PM


所有的时间均为北京时间。 现在的时间是 08:35 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多