concrete pier reinforcing
i have seen many large embedded concrete pier foundations for billboard sign columns and transmission tower columns placed without any pier reinforcing.
i assume the area of steel of the column itself (which is embedded deep into the piers) is thought to provide the minimum steel requirement and also to transfer axial load through the pier so that no horizontal ties are required.
if the pier extends a few feet above ground, should there then be minimum vert. reinforcing around the pier perimeter to control minor cracks people may see (like light poles in parking lots)? or is differential movement required for significant cracks, like a slab on grade???
check out our whitepaper library.
haynewp...in my area, just about everything gets reinforced because of the significant moment at the top of the shaft due to wind loads. if the columns are indeed embedded deeply into the shaft or pier, then theoretically there might be no significant reinforcement issue; however, don't neglect the stress concentrations developed by embedded columns on the concrete. if a column has significant bending stresses, it imparts those to the concrete, even if the stiffness of that section is greatly increased.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
concrete mix= reinfocing for exterior composit deck huangyhg 产品功能分析 0 2009-09-08 12:19 PM
concrete corrosion in partial saturated condition huangyhg 产品功能分析 0 2009-09-08 11:54 AM
chapter 4 preliminary design properties of concrete huangyhg 产品功能分析 0 2009-09-07 11:23 PM
big concrete pier huangyhg 产品功能分析 0 2009-09-07 03:45 PM
anchorage into concrete pier pier sizing huangyhg 产品功能分析 0 2009-09-07 12:01 PM


所有的时间均为北京时间。 现在的时间是 03:42 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多