默认 post-tensioning restrain

post-tensioning restraint
i am involved in prelim design of multi-story condo with flat plate construction, and c.i.p. elevator/stair cores for lateral load resistance. we would like to post-tension the slab due to bay sizes as large as 30'x30'. the cores occur near each end of the building, which is a very unfavorable layout with respect to restraint forces due to post-tensioning of the flat plate. the 6th edition pti manual fig 6.4 has suggested temporary release details where the slabs intersect with the walls. however, that does not seem real practical for 4 sided core areas where the slab wraps completely around the core. i would appreciate any input on how others have dealt with this problem.


yikes...sounds like a tough issue to get around.
i'm assuming you are post-tensioning both directions and the long direction stretching from end to end (core to core) would be restrained by the cores and prohibit the natural shortening in the length of the slab.
the first blush thought that popped into my head was separating the building into two halves, each associated with one core, using a temporary "missing" pour strip (could even be one bay wide) and post-tensioning each half separately. then come in later and tie the two together after the initial shrinkage.
you would still have to deal with some sort of diaphragm chord force element on either side of the floor width, but perhaps this could be done.
the only other idea would be to construct one core with punched out or missing walls in the relevent direction, sort of taking the guts out of its stiffness, and then filling in the walls later to provide the necessary lateral strength/stiffness.
pour strips that wrap completely around the core can be done. of course you would need to shore the unsupported slab edges which the contractor may not like. but i have done it before.
a pour strip across the slab half way between the cores works as long as there a few spans between the cores, at about 1/4 point in one span.
this will get the p/a into the slab but you still have the problem of restraint to shrinkage and temperature shortening as the poour strip will probably be closed after one or two weeks and there will be a lot more shortening to come. to cater for this, you will need significant reinforcement top and bottom in the slabs as well as the tendons.
if you want to do the calculations for this reinforcement, you cannot use the aci/pti average moment logic as checking for crack control requires you to check for the actual moments and stresses in each area of slab.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
post-tensioning only portions of a structure huangyhg 产品功能分析 0 2009-09-15 01:55 PM
post-tensioning design 9adapt procedure0 huangyhg 产品功能分析 0 2009-09-15 01:54 PM
post tensioning between very stiff members huangyhg 产品功能分析 0 2009-09-15 01:48 PM
low-end post-tensioning jacks huangyhg 产品功能分析 0 2009-09-10 11:52 AM
deck-railing post connection huangyhg 产品功能分析 0 2009-09-08 04:37 PM


所有的时间均为北京时间。 现在的时间是 09:45 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多