默认 modification of existing bar joists

modification of existing bar joists
need some help/advice with the following situation proposed an architect. a new elevator shaft and stairs are intended to be installed within an existing 3-story, 25 year old building. framing system is 18" 'h' series bar joists @ 24" o.c. supported on exterior 4" brick/4" block (i'm assuming composite) w/ 4-1/2" concrete on decking.
the plan at the elevator is to build the shaft up thru the vertical space while the joists are left in place (removing the concrete and decking within the shaft space) and then provide some sort of connection/stiffening of the joist at the masonry walls. after the joist is supported the joist within the space can be removed.
the stair would be supported on new steel beams which would also support the existing bar joists, also cut back.
has anybody done anything similar to this before. i do plan on contacting some joist manufactures and possibly sji but wanted to get some other opinions, too.
thanks in advance.
check out our whitepaper library.
if you cut or change the joists in any fashion, you will void the manufacturer's warranty on the product.
i strongly suggest going to the original manufacturer, if available, and involve them in the changes. if they are out of business or not available, the sji is a good start.
mike mccann
mccann engineering
msquared48, i doubt that a 25 year old building still has a warranty of any kind, wouldn't you think?
we've done this numerous times. fairly straightforward.
plot the joists shear and moment capacity diagrams (re
jae:
thanks for the reference.
more than likely you are right, but i would still check it out first. strange things do happen...
mike mccann
mccann engineering
as jae said, we have done this sucessfully numerous times. i recommend a site visit to field measure the joists including panel points locations. this may affect how the reinforcement is detailed since all joists are not manufactured the same.
i've run into this situation a number of times....
field measure the joist.
analyze the existing joist as a truss
analyze the new configuration as a truss.
thanks for the replies, you've all reinforced what i was thinking. it all seemed fairly straightforward, i just wanted to make sure there wasn't anything obvious that i was overlooking.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
galvanizing bar joists huangyhg 产品功能分析 0 2009-09-09 02:18 PM
existing open web steel joists huangyhg 产品功能分析 0 2009-09-09 08:56 AM
coverplating existing columns huangyhg 产品功能分析 0 2009-09-08 02:16 PM
altering existing open-web bar josi huangyhg 产品功能分析 0 2009-09-07 11:11 AM
国家标准全文数据库系统-机械卷 共计 3143 个标准 taobao American standards 0 2009-04-26 08:55 PM


所有的时间均为北京时间。 现在的时间是 04:41 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多