默认 new progress of montreal bridge collapse

new progress of montreal bridge collapse
quote:
can we handle the truth? we're going to have to. so is the transport department. it can start by putting someone in charge of the island's transport infrastructure who isn't going to try to hide problems under a coat of cement.fff">
a coat of cement....the writer certainly knows all about structures, eh?
subscription to montreal gazette seems to be required at this late date...
hg
oops. when i found that, it was still free and open.
here i paste the article as follows:
contractor says he was never ordered to fix overpass bars
william marsden, the gazette
published: thursday, may 03, 2007
a senior transport quebec engineer claimed yesterday that in 1992 he ordered additional reinforced steel bars to be inserted in the joints of the de la concorde overpass to strengthen the structure because the original steel was not properly installed.
but there is no evidence in the debris of the fallen structure that the additional steel bars were ever installed and the contractor who supposedly installed them said he never got the order.
furthermore, evidence before the johnson commission hearings into the collapse last sept. 30 of the overpass indicates that the additional bracing may not have been added because of a lack money.
tiona sanogo, 59, who is the senior engineer in charge of all highway structures in montreal, told the hearings that during repairs to the overpass in 1992 he noticed that the steel reinforcement bars had not been properly installed when the overpass was built in 1970.
he said he order the contractor to install "in several places" additional steel bars to add strength to the support columns of the overpass.
he claimed the work must have been done because permission was given to pour the cement over the bars.
but primo scapin, owner of dims, which was the company that repaired the joints, said the transport ministry never ordered him to install new steel bars.
he also said that he had suggested the ministry install new neoprene supports because the old ones had deteriorated dropping a section of the bridge about an inch. he said the government didn't have the money to pay for them.
unauthorized reproduction or linking forbidden without express written permission.
quote:
can we handle the truth? we're going to have to. so is the transport department. it can start by putting someone in charge of the island's transport infrastructure who isn't going to try to hide problems under a coat of cement.fff">
a coat of cement....the writer certainly knows all about structures, eh?
subscription to montreal gazette seems to be required at this late date...
hg
oops. when i found that, it was still free and open.
here i paste the article as follows:
contractor says he was never ordered to fix overpass bars
william marsden, the gazette
published: thursday, may 03, 2007
a senior transport quebec engineer claimed yesterday that in 1992 he ordered additional reinforced steel bars to be inserted in the joints of the de la concorde overpass to strengthen the structure because the original steel was not properly installed.
but there is no evidence in the debris of the fallen structure that the additional steel bars were ever installed and the contractor who supposedly installed them said he never got the order.
furthermore, evidence before the johnson commission hearings into the collapse last sept. 30 of the overpass indicates that the additional bracing may not have been added because of a lack money.
tiona sanogo, 59, who is the senior engineer in charge of all highway structures in montreal, told the hearings that during repairs to the overpass in 1992 he noticed that the steel reinforcement bars had not been properly installed when the overpass was built in 1970.
he said he order the contractor to install "in several places" additional steel bars to add strength to the support columns of the overpass.
he claimed the work must have been done because permission was given to pour the cement over the bars.
but primo scapin, owner of dims, which was the company that repaired the joints, said the transport ministry never ordered him to install new steel bars.
he also said that he had suggested the ministry install new neoprene supports because the old ones had deteriorated dropping a section of the bridge about an inch. he said the government didn't have the money to pay for them.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
bridge collapse in mn part 2 huangyhg 产品功能分析 0 2009-09-07 05:04 PM
【转帖】sample Problems For Cbuilder 2009 9the Cbuilder 2009 Librari yang686526 DirectDWG 0 2009-05-07 03:18 PM
【转帖】how can i avoid the assertion yang686526 DirectDWG 0 2009-05-05 12:13 PM
【转帖】哪位高手指点一下下边lisp的怎么用 yang686526 数据库ObjectDBX 0 2009-04-28 12:13 PM
哪位高手指点一下下边lisp的怎么用 yang686526 ObjectARX(AutoLISP) 0 2009-04-26 06:19 PM


所有的时间均为北京时间。 现在的时间是 08:12 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多