默认 hook

hook
i am checking a pedestal and footing design.
the rebar on the pedestal has hook at the bottom
and at the top.. i understand the hook the bottom
but the top, is this still necessary?
check out our whitepaper library.
i don't ever hook pedestal vertical bars at the top.
could it be for an uplift situation?
hooks in the verticals at the top make it more difficult to pour the pedestal. an alternate to the top hooks may be separate hairpins or longer anchor bolts to overlap more with the rebar (if possible).
that would be my guess.
i just talk to the originator he said because the development lenght is not enough..
is this correct logic.. i'm assuming you should extend the hook at the bottom to meet the development lenght..
not put hook at the top..
development length was = 47db (aci.12.2.4)
but what he did was this length from top of footing to top of pedestal.. that's why he hooked it because pedestal is short..
shouldnt 47db be top of footing all the way to bottom of footing for development length
development length needs to happen above and below the joint between the pedestal and the footing. it can, however, be modified by the ratio of as required to
as provided.
so he's wrong. it's between footing and pedestal. not going to the top it's useless and weird
ok i got the idea but still a bit confused he was talking about double development length.. they should have the same developement lenght at the top and the bottom.. due to tension..
he has a point but somehow i'm not totally conviced..
what if the pedestal is too short and small that development lenght of 47db is not possible?
if the pedestal is too short, you can use smaller bars (with less dev. length) or use more steel and then proportion down the dev. length by the ratio of
as required to as provided. another option is to eliminate the pier and have the column sit directly on the footing.
most pedestals have way more vertical steel then required and he should be proportioning down the dev. length by the ratio of as required to as provided.
edwin17th17,
hook at the top is sometimes required under following situations:
1. uplift in the column
2. size of pedestal is not ok for concrete breakout cone.
3. rebar is provided in pedestal to prevent the splitting/breakout of concrete due to pulling out of anchor bolt. to transfer the tensile forces from concrete to these rebar, you need to have sufficient length to fully develop.
if the length can not be provided as per code requirements, then one need to provide a 90 or 180 degree hook.
we have to hook pile dowels into cap beams all the time to develop the dowels into the cap and keep the cap from pulling off right over the dowels.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
hook development length huangyhg 产品功能分析 0 2009-09-09 04:54 PM
development and hooks huangyhg 产品功能分析 0 2009-09-08 06:29 PM
crane hook design -short deep cantilever beam huangyhg 产品功能分析 0 2009-09-08 02:33 PM
concrete development length for hook huangyhg 产品功能分析 0 2009-09-08 12:01 PM
【转帖】对于hook函数的一点认识 huangyhg vc编程 0 2007-03-27 11:53 AM


所有的时间均为北京时间。 现在的时间是 10:46 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多