默认 concrete slab on grade expansion joint questions

concrete slab on grade expansion joint questions
i am in the process of designing the joint pattern for a manufacturing building.
i have located the control joints and construction joints and i am now considering whether to include an expansion joint. right now the reinforcing (heavy mesh for the 6" slab) in the slab stop at the construction joints.
generally, the slab is 6" thick, 80 feet wide, and 800 feet long. i say generally, because there is a 8" thick slab strip that is 450 feet long and 15 feet wide also.
there are the usual traffic aisles, manufacturing aisles, platforms, racks, crane columns, utility trenches scattered throughout the structure.
the building will be heated in the winter with no cooling in the summer.
the slab will be poured in the summer when the building is enclosed. possible temperature at time of pour could be in the range of 80-100 degrees fahrenheit.
questions
1. is there a way to estimate the drying shrinkage of a slab?
2. would you include an expansion joint(s)?
expansion joints are common in outdoor slabs, but are not so common in interior slabs. the temerature range is not that wide.
for most concretes, shrinkage after two years is between 500 and 700 millionths. the commonly accepted values are "low shrinkage" 0.0005 inches per inch; "medium shrinkage" 0.0006 inches per inch; "high shrinkage" .0007 inches per inch.
many factors affect the degree of shrinkage, such as slump, temperature, time period of haul in mixer, number of revolutions at mixing speed, cement type used, aggregate size, aggregate quality and the use of admixtures.
pca recommendation for joint spacing of a 6" slab is between 12 and 15 feet for a slump ranging between 4-6 inches respectively, and 18 feet for a slump less than 4 inches.
thank you for the shrinkage information.
i am okay with the joint spacing.
my main question is whether to include an expansion joint or not.
some additional information concerning possible temperature swings. project is located in the central plains of the us. building will be heated during the coldest months. building will not be cooled. high temperatures in the summer can get to 100 degrees fahrenheit and range from 80-100.
will building have an expansion joint? if so, then i would recommend a slab ej at that location.
building is a pre-engineered metal building with 3 expansion joints.
the location of the building expansion joints is not really condusive for the slab expansnion joints because of equipemnt and factory operations.
if you building has expansion joints i would consider them in the slab. however, i don't think they are required.
building expansion joints and slab expansion joints are not going to be at the same location.
not anyway possible because of factory operations and equipment lay-out.
is your slab directly attached to your building? i don't think it will be of any importance to match your expansion joints. in my opinion building expansion joints and slab expansion joints address different issues. you will find that there is not much good documented information on slab-on-grade construction. it is much more of an art than a science.
we always include an ample amount of construction joints/control joints so that we don't need an expansion joint. unless they plan on pouring the entire slab at once (which won't happen) you will have quasi-expansion joints everywhere.
hopefully this document will help you decide.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
 


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
concrete roof slab load huangyhg 产品功能分析 0 2009-09-08 12:34 PM
concrete mix= reinfocing for exterior composit deck huangyhg 产品功能分析 0 2009-09-08 12:19 PM
chapter 4 preliminary design properties of concrete huangyhg 产品功能分析 0 2009-09-07 11:23 PM
basketball court slab on grade huangyhg 产品功能分析 0 2009-09-07 02:40 PM
as3600 concrete strength for slab on ground huangyhg 产品功能分析 0 2009-09-07 12:53 PM


所有的时间均为北京时间。 现在的时间是 04:42 PM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多