默认 becoming the eor inadvertently

becoming the eor inadvertently
suppose a building was originally designed, drawings were sealed and submitted, permits approved, and construction has begun. now during construction, the original engineer of record can no longer be reached or is unavailable for whatever reason. as this building is being constructed in the real world, something may come up that requires additional engineering input. my question is what can i as an unrelated engineer do without becoming the new eor (which means adopting the previous engineer's work as my own - a major deal not to be taken lightly).
i realize answer will greatly depend on scope of new work. say there is a 10,000 square foot home where they are adding one additional post on the porch. if i design the post, did i take on design responsibility for the whole project? i assume the answer may also depend on timing. ten years after project was completed and then adding the post would hopefully keep me from being the eor for original project.
as far as i can tell state laws are a little vague on this topic. what are other folks doing in this regard?

you can produce drawings for a small portion of the building and be the eor for that portion only. you should clearly indicate the portion that are new (which you are responsible for) and clearly identify the elements that are existing (portion the eor for the building is responsible for).
you, as the eor for the new work shall also be responsible for verifying the adequacy of any existing elements that receive extra loading than they were originally designed for.
i suppose this is true in all areas but never know...
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭



所有的时间均为北京时间。 现在的时间是 06:59 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多