默认 pile driving monitoring

pile driving monitoring
i'm preparing a proposal to monitor a four story brownstone adjacent to a new construction site where piles will be driven. im going to do a complete visual structural inspection of the building before work begins. then i will make periodic visits at owners request to see if anything has changed. besides monitoring for cracks and existing cracks getting larger, foundation settlement, and general structural problems is there anything else i should consider. if vibration seems excessive i would bring in a testing lab to monitor interior vibrations. i have a lot of experience in building inspection, rehab, and renovation...just wondering is anyone had any experience or advice on this specific topic.
jjeng2....have the vibration monitoring done...if claims are made after the fact, you have no way of knowing if the vibrations exceeded damage thresholds.
monitoring should be done on the exterior foundation of the existing building and in the ground at the point on the existing property closest to the pile driving.
you might consider going over the existing, and adjacent existing building to record all cracks and other observable distresses. a photographic record of these current distresses would be warranted.
that way, after the piles have been installed, you have proof that existing cracks were indeed existing and therefore not caused by the driving work.
good advice - use the same level of care you would for deep excavations near existing structures.
if the existig building foundation is not piled, like mat, or footing in bad soil, the soil balance can be very precise, better get some distance between the buildings, independently of vibrations.
put some strain gauges on some of the cracks. especially ones on the walls perpendicular to the pile driving. and at least one seismograph in the basement. take elevations on floor slabs and window sills to the nearest one thousandth of an inch. give a copy of the elevations to the piledriver's insurance company and the general contractor's also.
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
pile design load factors huangyhg 产品功能分析 0 2009-09-15 12:24 PM
pile caps - helical piles huangyhg 产品功能分析 0 2009-09-15 12:23 PM
pile cap huangyhg 产品功能分析 0 2009-09-15 12:22 PM
h piles - end bearing huangyhg 产品功能分析 0 2009-09-09 03:39 PM
h pile huangyhg 产品功能分析 0 2009-09-09 03:39 PM


所有的时间均为北京时间。 现在的时间是 09:43 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多