默认 low heat cement in machine foundation

low heat cement in machine foundation
it is quite common to have thick slab [800mm to 1200mm or more] foundation for heavy machines in minining sites. in such cases we should use low heat cement. theoretically, special form work with heat insulators are required for such type of massive pours.
i have not seen any low heat cement and special formwork for foundation design so far in the projects that i was involved with. my question is, if it is really mandatory to use low heat cement and special formwork for machine foundation? and if we do not use that, there is a possibility that cracking will appear on the slab and time to time those cracks are to be attended to. probably the structural strength of the foundation will not be in jeopardy, because, in majoirity of cases, the thickness is governed by the dynamics of the equipment.
ideally we should use low heat cement and special formwork; but in reality it is difficult and very expensive to follow it up in remote mining sites. using standard concrete with heavy reinforcement [for crack control] and standard formwork is the easy option. please share your experience in this subject.
your experience and frustration is common. rare to be able to control concrete temperature well on remote sites. casting very early in the day should help some. for large projects, can sometimes get ice plants to cool mixing water.
in your 800 to 1200 thick footings or slabs, lack of compaction is probably the most likely cause of cracking. consolidation continues after initial vibration, thus creating plastic settlement cracks directly over the top bars. this can be largely avoided by revibration, and the time to do this depends a lot on the temperature of the concrete when placed.

hokie66, thank you for your response - this is what i am experiencing. sorry, i could not respond earlier - my computer crashed! it is working now.
regards
am
__________________
借用达朗贝尔的名言:前进吧,你会得到信心!
[url="http://www.dimcax.com"]几何尺寸与公差标准[/url]
huangyhg离线中   回复时引用此帖
GDT自动化论坛(仅游客可见)
回复


主题工具 搜索本主题
搜索本主题:

高级搜索
显示模式

发帖规则
不可以发表新主题
不可以回复主题
不可以上传附件
不可以编辑您的帖子

vB 代码开启
[IMG]代码开启
HTML代码关闭

相似的主题
主题 主题发起者 论坛 回复 最后发表
low 7-day concrete breaks huangyhg 产品功能分析 0 2009-09-10 11:48 AM
heat straightening of steel beams huangyhg 产品功能分析 0 2009-09-09 04:00 PM
foundation cracking and settling huangyhg 产品功能分析 0 2009-09-09 01:24 PM
crack in foundation wall huangyhg 产品功能分析 0 2009-09-08 02:20 PM
connecting a new foundation to an existing huangyhg 产品功能分析 0 2009-09-08 01:09 PM


所有的时间均为北京时间。 现在的时间是 09:41 AM.


于2004年创办,几何尺寸与公差论坛"致力于产品几何量公差标准GD&T | GPS研究/CAD设计/CAM加工/CMM测量"。免责声明:论坛严禁发布色情反动言论及有关违反国家法律法规内容!情节严重者提供其IP,并配合相关部门进行严厉查处,若內容有涉及侵权,请立即联系我们QQ:44671734。注:此论坛须管理员验证方可发帖。
沪ICP备06057009号-2
更多