![]() |
underpinning with concrete and drypack
underpinning with concrete and drypack
i am specifying underpinning with concrete, with the top 2 inches to be drypacked. should i provide a time interval between the concrete placement and the drypacking work. i had in mind 4 days from concrete placement to drypacking work (drypacking with non shrink grout) and then additional 3 days for drypack to cure before going to the next set of pins, thus for a total of 7 days. does concrete shrink only between the time of placement and initial set, or is this a gradual process continuing. |
| 所有的时间均为北京时间。 现在的时间是 07:00 PM. |